Summary
Some risk. Buying off-plan in Tijuana carries real risk today, but the main danger is delay, not fraud. In June 2026, 64 of the 80 stalled building projects in Tijuana were waiting for a power hookup, and with about 25 months of unsold new homes on the market, reselling a pre-sale flat at a profit is hard.
Eight of the nine risks we track read Some risk, and only changes to fees and finishes read Low risk. None reads High risk: we found no official action in the last 12 months against several projects at once, such as closures or a state list of irregular projects. The biggest are a finished building with no power, a pre-sale contract nobody wants to take over, and rents below what the sales pitch promised.
Electricity comes first. In June 2026, Tijuana's economic development secretary said the lack of grid capacity, not permits, was what held those projects back. The federal power company, CFE, has since announced new network works, but no date for any single tower.
A delay can turn into a cash problem. Buyers at KYO Ilán, in Colinas de Baja California, were still waiting in August 2026 for flats due in August 2023, and some were also waiting for refunds. The developer promised to deliver or repay within six months.
Taking the keys does not make reselling easy either. Softec counted 4,219 new homes for sale in 118 projects across Tijuana, Rosarito and Ensenada in the third quarter of 2026, at about MXN 51,800 per m² on average. Finished flats compete with new launches, so a buyer has little reason to take over someone else's unfinished contract.
Renting out is the next test. Tijuana's real estate agents reported rent cuts of 10% to 15% in some zones during 2025, and asking rents for flats fell 7.5% across the city in the 18 months to November 2026 (Propiedades.com). A brochure rent from launch day can be out of reach even if the flat is handed over on time.
Outside the tower districts, the weak spots are water and municipal services. Over 100 estates had not been handed over to the water utility in April 2026, and 82% of 957 neighborhoods and estates had not been taken over by the city in September 2026. Contracts and permits bring their own risks, from unregistered pre-sale contracts to the 4,000 signatures gathered against towers in Cañada Azteca, in Playas de Tijuana.
So before paying a big deposit, ask for proof of power and water capacity, construction funding, valid permits, realistic rents and penalties for late delivery. A launch discount is worth little until those documents are on the table.
Our Tijuana pre‑construction risk table
Our table rates 9 types of risk for anyone buying a new home in Tijuana before it is finished, with a recent local case for each one.
It also shows how often or where each problem shows up, what a buyer stands to lose and which document protects you before you pay, so you can tell tower problems apart from those of new housing estates.
If you want real answers from the field about a specific home or street, ask a pro in Tijuana for free.
| Type of risk |
Risky to buy off-plan? our short answer |
Recent Case in Tijuana, with date |
How Often or where |
What You Lose if it happens |
What Protects You before you pay |
Data confidence iHigh: direct data for this type of risk. Medium: one strong source, or several pointing the same way, with our own estimate. Low: few signals, an order of magnitude. |
|---|---|---|---|---|---|---|
| Late delivery: no power hookup | Some risk | 64 of 80 stalled projects wait for CFE power (June 2026) | 64 of 80 projects | Months to years of delay | Contract with a delivery date and penalty; CFE power letter (factibilidad) for the tower | Medium |
| Late delivery: developer trouble | Some risk | KYO Ilan: 120 flats due Aug 2023, still waiting in Aug 2026 | A few named towers | 3+ years; deposits stuck | A developer with finished towers; payments tied to building stages | Medium |
| Hard to resell before the keys | Some risk | About 25 months of unsold new homes at today's pace (Softec, Q3 2026) | Every tower area | Selling at or below what you paid | Buy to live in, not to flip; compare with finished resale nearby | Medium |
| Rents lower than the sales pitch | Some risk | Asking rents for flats down 7.5% in about 18 months (Propiedades.com, Nov 2026) | Colonia Juárez, Zona Centro, Agua Caliente (rents down 10% or more) | 2-3 points of yield | Check today's rents in finished towers, not the brochure | Low |
| Water not connected | Some risk | Over 100 estates not handed to the water utility (Apr 2026) | Estates more than towers | Poor water, private trucks | CESPT feasibility letter and paid connection rights | Medium |
| Estate not handed to the city | Some risk | 82% of 957 estates not handed over (Sep 2026) | Estates, east and south | Residents pay for roads and lights | Ask if the estate is "municipalizado" | Medium |
| Contract without protection | Some risk | Pre‑sale contracts must be registered with PROFECO since 2022 (NOM-247); many are not | Common, no count | Weak claim if it goes wrong | Ask for the PROFECO registration number of the contract | Low |
| Neighbours fight the project | Some risk | Cañada Azteca (Playas): march of 100+, 4,000 signatures against towers (2026) | Playas de Tijuana | Permits frozen, delays | Check the land‑use permit and any lawsuit before signing | Medium |
| Fees and size that change | Low risk | Developer sells with a small deposit and payments later (e.g. MXN 200,000 down, about MXN 25,000 a month to spring 2027) | Common in new towers | Final price or building fees higher than sold | Get building fees and finishes written in the contract | Low |
New homes for sale in Q3 2026: 4,219 unsold in 118 projects across Tijuana, Rosarito and Ensenada, about MXN 51,847 per m² on average (Softec). Developers also pay water connection rights to the utility (CESPT) and must get a water feasibility letter, valid 6 months, before selling. Rule (ours), risk by risk: High risk = official action in the last 12 months against several projects (closures or a state list of irregular projects). Some risk = one named case in the last 2 years, or a market or contract condition that puts buyers' money at risk. Low risk = no case in the last 2 years.
How we got these numbers. We analyzed 94 sources and 316 signals on Tijuana (Softec via Centro Urbano and ADI, the city's economic development office via the press, Semanario ZETA, the NOM-247 standard, CESPT procedures, CMIC). The table itself uses 16 signals from 11 sources. Rows are the risks reported in Tijuana.
Source: TheLatinvestor property database, November 2026.
Ask a Tijuana pro to check
the developer, for free.
They know which developers deliver on time.
Message a proIs it risky to buy pre-construction in Tijuana now?
Some risk. Buying off-plan in Tijuana is risky today, mainly because a developer can finish a building and still leave buyers waiting for electricity, while weak resale and rental markets eat into the investment.
We rate 8 of our 9 risks Some risk and 1 Low risk. None reaches High risk, which on our rule needs official action against several projects in the last 12 months. The three that weigh most are a building stuck without a power hookup, a pre-sale flat that is hard to resell before the keys, and rents that come in below the sales pitch. A legally sold, attractive flat can still leave its owner unable to move in, collect rent or sell without a loss.
The power shortage is the clearest reason a finished-looking building may be unusable. In June 2026, Tijuana's economic development secretary, Pedro Montejo Peterson, said 64 of the 80 delayed building projects in the city were held up by the lack of electrical capacity, not by permits. In September 2026, Uniradio quoted energy engineer Rolando Escobedo saying Tijuana had 32 substations and needed 5 more.
There is also a money problem even when building goes to plan. Softec's third-quarter 2026 study found 4,219 new homes for sale across Tijuana, Rosarito and Ensenada, at an average of MXN 51,847 per m². A buyer who wants out before the keys competes with all of them, and the fair comparison for an off-plan flat is a finished flat nearby.
Other risks depend on the kind of project. Water hookups and the city's takeover of streets and lighting matter most in housing estates, while unregistered contracts and neighbor opposition come down to documents and permits. Changes to fees and finishes are a smaller worry when floor plans, finishes and fees are written into the contract.
We prefer a funded tower with confirmed power and water capacity, a developer with finished buildings behind it and delivery terms you can enforce. A rendering, a reservation receipt and a promised return cannot replace those documents.
The table below shows each type of risk with our verdict, where it shows up, what you lose and the latest dated figure we found outside our table.
| Type of risk | Our verdict | How often (or where) | What you lose | Latest outside figure |
|---|---|---|---|---|
| Late delivery: no power hookup | Some risk | 64 of 80 projects | Months to years of delay | Tijuana has 32 substations and needs 5 more (Uniradio, September 2026) |
| Hard to resell before the keys | Some risk | Every tower area | Selling at or below what you paid | 4,219 new homes for sale in 118 projects (Softec, Q3 2026) |
| Rents lower than the sales pitch | Some risk | Colonia Juárez, Zona Centro, Agua Caliente | 2-3 points of yield | Asking rents for flats down 7.5% in about 18 months (Propiedades.com, November 2026) |
| Late delivery: developer trouble | Some risk | A few named towers | 3+ years; deposits stuck | KYO Ilán Tower A 70% built, due January 2027 (ZETA, August 2026) |
| Water not connected | Some risk | Estates more than towers | Poor water, private trucks | Water feasibility letter valid 6 months (CESPT registry, September 2026) |
| Estate not handed to the city | Some risk | Estates, east and south | Residents pay for roads and lights | Special city program for abandoned estates (ZETA, September 2026) |
| Contract without protection | Some risk | Common, no count | Weak claim if it goes wrong | NOM-247 pre-sale contract rules in force since September 2022 |
| Neighbours fight the project | Some risk | Playas de Tijuana | Permits frozen, delays | March of more than 100 people against Cañada Azteca (N+, April 2026) |
| Fees and size that change | Low risk | Common in new towers | Final price or building fees higher than sold | Some building materials up to 30% dearer (CMIC, September 2026) |
Can a Tijuana condo sit finished for months without electricity?
Yes, a Tijuana condo can look finished and stay unusable for months when the developer has no confirmed permanent power connection from CFE.
This is our sharpest infrastructure warning. NDT Noticias de Tijuana reported on June 12, 2026 that 64 of the 80 delayed building projects in Tijuana were held up mainly by the lack of electrical capacity, according to the city's economic development secretary. He said talks with CFE on expanding the grid were taking place in Mexico City because of the size of the work needed.
The whole grid is stretched. In September 2026, Uniradio reported that Tijuana ran 32 substations and needed 5 more, most of them over 30 years old. The same month, N+ reported that CFE had brought the La Encantada substation into service and was upgrading the Panamericana, Durazno, Toreo, Alamar and Seminario substations. Those works are real, but none of them comes with a hookup date for a given tower.
Some builders now pay for their own power. AFN reported in June 2026 that some developers were financing private substations or power lines to reach CFE's network. That can solve one project's problem, but a private transformer does not prove CFE has approved enough permanent capacity for every flat, lift, water pump and shared area.
A CFE feasibility letter is only the starting point. Tijuana asks for power and water feasibility documents when it approves a new development, and the final hookup needs further works and approval. Ask the developer which part is done, who pays for what remains and whether the capacity covers the lifts, pumps and the whole building.
Timing matters as much as the letter. A building that gets its permanent connection a year after the promised handover leaves buyers paying rent elsewhere, or loan installments on a flat they cannot use.
So the question to ask is simple: when exactly will CFE switch this building on, and what document proves it? If the developer cannot answer, price in a long delay.
Can Tijuana buyers get trapped waiting for refunds like at KYO Ilán?
Yes, buyers in a troubled Tijuana pre-sale can end up waiting first for the flat and then for their refund, as the KYO Ilán case shows.
ZETA reported on August 3, 2026 that KYO Ilán's 120 flats in Colinas de Baja California were still not delivered, three years after the delivery date of August 25, 2023 written in one buyer's contract. Buyers who wanted out were also waiting for their money. That is the worst combination: no home, and the cash meant for another home locked up.
Several problems piled up. ZETA named Koinox Developers, represented by Desarrollos Adalid, whose spokesman blamed contractors that went bankrupt after the pandemic, material prices that raised costs by up to 70%, three months of work stopped by neighbor protests over water, and a defective facade. Redoing that facade took 10 months and cost more than MXN 15 million.
Koinox gave a new timetable and said it could fund the remaining work. According to ZETA, Tower A was 70% complete and due in January 2027, with Tower B needing about 10 more months. Eight buyers had formally asked for refunds and five had been repaid, according to the company.
The buyers learned the limits of a refund promise. One couple who paid nearly MXN 500,000 said their 120-working-day refund deadline passed on July 6 without payment. A written promise to repay is worth little if the company cannot pay when the money is due.
Building costs have also been hard to predict. CMIC Tijuana reported steel-related materials up as much as 20% in April 2026, and El Imparcial quoted the chamber on some materials up as much as 30% in September. No official count of troubled developers in Tijuana is published.
What protects you is a developer with finished towers, the source of the money for the remaining work and payments tied to building stages. Paying in step with verified progress keeps a buyer from funding too much unfinished work upfront.
Can Tijuana developers hand over new homes without reliable water?
Yes, a new home in Tijuana can have pipes and taps but no dependable water when the developer has not finished the hookup and handover to the water utility, CESPT.
This is a real concern for housing estates, less so for single towers. In April 2026, ZETA reported that over 100 estates had not been formally handed over to the Comisión Estatal de Servicios Públicos de Tijuana. The report looked at Real del Mar, where residents complained of contaminated water and disputes over who should maintain the network.
CESPT has a formal feasibility process. The Baja California state registry of procedures describes a technical opinion on whether water or sewage service can be provided, valid for 6 months, which states whether service is possible and on what conditions. A positive opinion helps, but its conditions may still require works or payments before water actually flows.
A separate CESPT procedure covers the water and sewage contract for new developments. The registry says the developer must pay the connection rights. That matters when a salesperson presents an unpaid hookup as something residents can sort out after moving in.
Water feasibility often comes with a bill. In June 2026, ZETA quoted the Baja California homebuilders' association, Canadevi, explaining that approval can depend on the developer paying for a tank, drains, a pump or other network works. Centro, Zona Río and La Cacho were named as areas where existing systems were saturated, while outer areas such as El Niño and Valle de las Palmas needed entirely new connections.
So feasibility, payment, finished works and CESPT acceptance each need their own proof. A buyer should ask for the CESPT opinion with its date, the receipt for the connection rights and the status of the handover to the utility.
Water also links to opposition. KYO Ilán's three-month stoppage came from neighbors protesting about their own water supply, which shows how a saturated network can delay a tower even before the hookup question arises.
Ask a Tijuana lawyer
today, for free.
They check the registry before you pay anything.
Message a proWho pays when a new Tijuana estate isn't handed over to the city?
Until Tijuana formally takes over a new housing estate, the developer or the residents may have to keep paying for roads, street lights and other shared services.
This is a real risk, concentrated in the estates of the east and south. In September 2026, ZETA cited city data showing that 82% of 957 neighborhoods and estates had not been formally handed over to the municipality. The count includes long-established neighborhoods, not only recent off-plan estates.
Paved streets and installed lights do not mean the city has agreed to maintain them. According to ZETA, the city already provides some services in places it has not formally taken over, which leaves hard questions about planning and public money. A buyer can find patchy services even in an estate where people already live.
The city now has a plan for abandoned estates. ZETA reported a 2026 special program offering a simpler handover route for developments whose builders had disappeared or stopped working. The program has conditions on basic works, paperwork and occupancy, so it does not take over every unfinished estate automatically.
Tijuana's urban administration office, the Dirección de Administración Urbana, lists the documents needed to approve a new development: service feasibility, land-use approval, drainage plans, environmental approval and proof of title. The city's later takeover of the estate is a separate step.
So ask the seller whether the estate is "municipalizado", meaning formally taken over by the city. If not, ask for the agreement that says who pays for roads, lighting and repairs until that happens.
A project can also have private water works still waiting for CESPT to accept them. The purchase contract should say who maintains and pays for those systems until both the water utility and the city have taken over. Without that clause, residents tend to end up paying.
Can you resell a Tijuana pre-sale condo before getting the keys?
You can resell a Tijuana pre-sale contract before the keys, but making a profit is far from guaranteed while developers are still selling competing new units.
We rate it Some risk. Developers hold about 25 months of unsold new homes at today's pace, down from about 47 at the end of 2025. Every tower area is exposed.
The latest count confirms the pressure. Softec's third-quarter 2026 study, reported by Centro Urbano on September 2, 2026, found 4,219 homes for sale in 118 projects in a market that covers Tijuana, Ensenada and Playas de Rosarito. Of those, 2,574 were flats in 76 projects, selling at about 102.8 a month.
That stock gives the next buyer choices. They can negotiate directly with the builder, or buy a finished flat they can inspect. A private seller needs a convincing reason to charge a premium for an unfinished unit when the developer is still selling the same layout.
The contract can block a quick exit too. Transferring a pre-sale contract may need the developer's consent, payment of what is owed or other formalities. Buyers need the clause that governs resale in writing, not a salesperson's promise that someone abroad can simply take over the installments. The lender, and for foreign buyers the notary and the bank holding the trust, may also need to approve the final structure.
So buy to live in rather than to flip, and compare the pre-sale price with finished resale flats nearby before you sign.
The table below shows Softec's third-quarter 2026 count of new homes in the Tijuana market, by type of home.
| Type of home | Projects | Homes in projects | Homes for sale | Sold per month |
|---|---|---|---|---|
| Flats | 76 | 5,848 | 2,574 | 102.8 |
| Detached houses | 26 | 2,921 | 1,323 | 39.9 |
| Gated house complexes | 14 | 824 | 166 | 23.4 |
| Duplex houses | 2 | 196 | 156 | — |
| All new homes | 118 | 9,789 | 4,219 | 167.8 |
Note: Softec's Tijuana market includes Ensenada and Playas de Rosarito, as reported by Centro Urbano on September 2, 2026.
Are Tijuana pre-sale rental promises too optimistic?
Yes, the rents quoted for Tijuana pre-sale condos are often too optimistic, especially when the pitch assumes tenants will pay top prices as soon as the building opens.
We rate it Some risk. Asking rents for flats fell 7.5% across Tijuana in about 18 months, and by 10% or more in Colonia Juárez, Zona Centro and Agua Caliente (Propiedades.com). Zona Río was the exception, up 9.7%. A fall of that size can cost an over-optimistic buyer 2 to 3 points of yield.
The agents' own figures back this up. In January 2026, AFN quoted the president of AMPI Tijuana, Dulce Belén Reynoso Reyes, describing rent cuts of between 10 and 15% in the last quarter of 2025, strongest in the expensive "zona dorada". In September 2026, Uniradio quoted an AMPI valuation expert describing flats re-let at US$600 instead of US$800, while stressing that rents were not falling everywhere in Tijuana.
The rent in a brochure can be far from what a tenant will pay. An agent may quote a furnished flat with a view in another tower, while the unit on offer is smaller, has unfinished amenities or carries higher monthly fees. A newly finished building can also release dozens of near-identical flats onto the rental market at once, right when every investor needs a tenant.
We start from asking rents, and signed leases where we can find them, for finished flats in the same area. Compare flats of the same size and furnishing, with the same parking and amenities, and ask which currency the lease is in. In a border city, a rent quoted in dollars is not a promise that local demand will hold at that level.
A late handover also delays the first rent check, and unfinished utilities can delay it again. A buyer who plans to live in the flat can wait more easily than an investor whose loan depends on the rent quoted at launch.
So base the numbers on today's rents in finished towers nearby, not on the brochure, and check how many similar flats the same building will release at once.
Can neighbors delay a new tower in Playas de Tijuana?
Yes, neighbors in Playas de Tijuana can slow down an off-plan tower when they challenge its permits, its effect on the environment or its water supply.
This is a real permit and building risk in our evidence, and Playas de Tijuana is where it shows most. In April 2026, N+ reported a march of more than 100 people against a planned housing and shopping development in Cañada Azteca, an area residents described as ecologically sensitive. By May 2026, ZETA reported that the group Defendamos Playas had gathered 4,000 signatures and was looking at formal complaints against the approvals.
Marches and signatures do not cancel a tower on their own. The risk for buyers is the time it takes to settle disputed permits or lawsuits while their money is tied to a delivery date.
At Cañada Azteca, the dispute was about what work had been authorized. ZETA described disagreements over whether permits for clearing and upkeep allowed much bigger earthworks, and calls to review changes in land use. Lawsuits matter most when a project depends on building more densely than the existing rules allow. A delivery date that assumes digging will go on uninterrupted is hard to believe while the basic permit is publicly disputed.
Tijuana's urban administration files are the place to start. The city requires land-use approval, infrastructure feasibility records and environmental documents where needed before it approves a development. Check the permit for the exact plot you are buying into, since the approval of the building next door means nothing for yours.
Playas is not the only place where residents push back. ZETA's June 2026 reporting on power shortages also described objections to new towers in established areas such as Hacienda Agua Caliente, and KYO Ilán lost three months to neighbors worried about water.
So check the land-use permit and any open lawsuit before you sign, and be wary of a delivery date that leaves no room for a dispute.
Ask a Tijuana agent
for free, before you sign.
They can visit and tell you what they see.
Message a proDoes a PROFECO contract protect Tijuana pre-sale buyers?
No, a pre-sale contract registered with PROFECO, Mexico's consumer protection agency, gives buyers clearer rights but cannot guarantee a finished flat or a fast refund.
Unregistered contracts are a real concern, because a sales document can look professional without matching the terms Mexican law requires. The standard NOM-247-SE-2021 came into force in September 2022. It requires residential developers to register their standard contracts with PROFECO and, for pre-sales, to disclose the plans, the property details, the price, the payment schedule and the guarantees.
The standard also covers late delivery. The contract must give the expected delivery date and the agreed penalty, with rules for genuine causes beyond the developer's control. It also covers cancellation and must show the PROFECO registration number and date. PROFECO's public register of standard contracts lets anyone look up a registered contract by company name, trade name or registration number.
Check the legal name of the company signing your contract. It must be the one responsible for building, transferring title and paying refunds, and a refund clause is only as good as that company's ability to pay.
Foreign buyers also need to plan the final closing. Tijuana sits in Mexico's restricted zone near the border, so foreign buyers of homes normally hold them through a bank trust, a fideicomiso, under the Foreign Ministry's rules. The trust, title papers and final deed can be ready later than the flat itself.
Match the floor plan, unit number, parking, delivery date and cancellation terms against the signed contract and its annexes. PROFECO registration cannot replace proof from CFE or CESPT.
The table below shows, for each type of risk, what protects you before you pay and which office holds the record you can check.
| Type of risk | Our verdict | What protects you (before you pay) | Record to check | Who holds it |
|---|---|---|---|---|
| Contract without protection | Some risk | Ask for the PROFECO registration number of the contract | Registered standard contract | PROFECO public register |
| Late delivery: no power hookup | Some risk | Contract with a delivery date and penalty; CFE power letter (factibilidad) for the tower | Feasibility letter and connection works | CFE |
| Water not connected | Some risk | CESPT feasibility letter and paid connection rights | Technical opinion and connection receipt | CESPT |
| Estate not handed to the city | Some risk | Ask if the estate is "municipalizado" | Handover status of the estate | City of Tijuana |
| Neighbours fight the project | Some risk | Check the land-use permit and any lawsuit before signing | Land-use approval for the plot | City urban administration (DAU) |
| Late delivery: developer trouble | Some risk | A developer with finished towers; payments tied to building stages | Deeds of past finished towers | Public property registry and notary |
| Hard to resell before the keys | Some risk | Buy to live in, not to flip; compare with finished resale nearby | Resale clause of the contract | Developer and notary |
| Rents lower than the sales pitch | Some risk | Check today's rents in finished towers, not the brochure | Leases of finished flats nearby | Local agents and owners |
| Fees and size that change | Low risk | Get building fees and finishes written in the contract | Plans and fee annex | Developer and notary |
Can a Tijuana developer raise fees or change the apartment after you pay?
Yes, final fees or finishes can surprise a Tijuana pre-sale buyer, although a detailed signed plan and fee schedule make this much easier to fight than a missing power hookup.
This is the one risk we rate as low. Developers often sell with a small deposit and payments later, for example MXN 200,000 down and about MXN 25,000 a month until spring 2027. That tells a buyer how the cash is collected, not whether the total includes parking, closets, appliances, utility setup or the building fees after handover.
Early sales drawings can change before the final plans are settled. NOM-247-SE-2021 requires developers to show the full project, the plans and a description of the home and its extras. It also covers written notice of changes and extra services agreed in writing. A verbal promise of certain finishes is far weaker than a contract annex naming the materials, the measurements and the exact unit.
The quoted price may leave out costs you pay after the keys. Building fees depend on what the finished building will actually run: lifts, pumps, security, parking systems, shared spaces and staff. A tower that has not opened cannot show its real running budget yet. We separate the estimated monthly fee from the binding question of who pays for hookups, changes and building costs before the condo association is up and running.
Rising building costs add pressure. In September 2026, CMIC Tijuana reported some materials up as much as 30%, and KYO Ilán's developer blamed material prices for raising its costs by up to 70%. Contractors may need more cash, but that does not allow a developer to raise a signed price. Any price-adjustment clause must say clearly when and how the price can change.
Keep the dated brochure, approved plans, signed list of finishes, payment schedule and fee estimate together. If the seller will not put an important promise in the contract, assume it will be hard to enforce later.
Which documents make a Tijuana pre-sale worth buying?
For a Tijuana pre-sale, we want proof of CFE power capacity, a CESPT water feasibility letter, valid permits, money to finish the work and a PROFECO-registered contract before trusting the sales timetable.
Start by sorting what the builder controls from what depends on a public body or utility. Plans, financing, the contractor and the payment schedule are largely in the developer's hands. Power and water depend on CFE and CESPT, and land use and the takeover of streets depend on the city. Each one needs its own proof and, ideally, a named person responsible for closing it.
The past year shows why. In June 2026, ZETA described power shortages holding up developers, and in April it reported on estates still waiting for CESPT to accept their water networks. By September, city officials were working through hundreds of estates not yet taken over. Each office handles a different problem, so one approval says nothing about the others.
Next, look at the money. Ask to see finished buildings by the same developer, the funds set aside for the remaining work and progress certificates tied to each installment. For investors, compare the promised rent with finished flats nearby. For foreign buyers, ask the notary and the bank holding the trust when the fideicomiso and the final deed can be signed.
Then check each record at the source. PROFECO's public register can confirm the contract, the city's offices can confirm land use, CESPT can explain a water feasibility letter, CFE can confirm power capacity and the notary can review the title. Emails from the sales team are weaker proof than the records held by those offices.
Timing matters too. Ask for these documents before the deposit, not after, because a deposit becomes hard to recover once the contract is signed. A developer with nothing to hide can usually produce most of them within days.
A pre-sale that passes all these checks can still be a good buy, especially for someone who plans to live in the flat and is not in a hurry.
So, is it risky to buy pre-construction in Tijuana now?
Some risk, in 8 of the 9 ways we track. Buying pre-construction in Tijuana is risky enough that a late handover should be treated as a real possibility, not brushed aside because of a promised date.
We would not rule out every unfinished flat, but every sales promise needs documents behind it. The biggest weakness is how easily a building can be finished without being ready to live in, rent out or resell.
The most pressing issue is electricity. A missing power hookup can stop people moving in even when the building looks complete, and the grid is being asked to serve new homes and new factories at the same time. Official statements and specialist reporting this year point to a grid that needs more substations. A developer with a confirmed, paid CFE connection is in a far better position than one counting on future grid upgrades with no date.
The next concern is getting your money back out. Reselling before the keys is painful when developers are still selling unsold flats and buyers can compare with finished alternatives. Rents below the sales pitch add a further problem for investors who need income right away to cover a loan and building fees. That is why we prefer a sensibly priced home bought to live in over a speculative pre-sale that only works if the buyer flips it quickly or earns the brochure rent.
The type of project decides which documents matter most. In tower districts such as Zona Río and Hipódromo, the timing of the power hookup and real rents deserve the closest look. In Playas de Tijuana, the Cañada Azteca dispute is a reason to check the land-use permit and any public objection for the exact plot. In the estates to the east and south, the city's takeover and CESPT's acceptance of the water network may matter more than any brochure.
KYO Ilán shows how a buyer can lose access to both the home and the refund while the builder tries to finish. It should change how a buyer handles payments during construction, refund promises and the identity of the company behind the contract.
How solid is our picture? Six risks carry Medium confidence and three Low (unprotected contracts, changing fees, rents below the pitch). Only two are backed by official counts, the stalled projects waiting for power and the estates not taken over by the city. For developer trouble, unregistered contracts, failed resales and disappointing rents, no 2026 citywide count is published, so we rate them from named cases and what buyers lose.
Tijuana pre-sales can still make sense when the developer proves power, water, permits, construction funding and delivery terms before the buyer commits serious money. The things to watch are the permanent CFE hookup, a current CESPT letter, the city's permit and takeover records, the PROFECO-registered contract and real rents in finished buildings nearby. Without them, a lower launch price can become an expensive way to wait.
Our methodology
Our data runs through November 2026. We assess 9 types of risk for anyone buying a new home in Tijuana before it is finished, covering late delivery, power and water hookups, contracts, neighbor opposition, resale, rents and changes to the promised home. For each one, our table gives our verdict, a recent case in Tijuana, how often or where it shows up, what a buyer can lose and what protects you before you pay.
We analyzed 94 sources and 316 signals on Tijuana, including Softec via Centro Urbano and ADI, the city's economic development office via the press, Semanario ZETA, the NOM-247 standard, CESPT procedures and CMIC. The table itself uses 16 signals from 11 sources. The rows are the risks reported in Tijuana.
Rule (ours), risk by risk: High risk = official action in the last 12 months against several projects (closures or a state list of irregular projects). Some risk = one named case in the last 2 years, or a market or contract condition that puts buyers' money at risk. Low risk = no case in the last 2 years.
Confidence is Medium for six risks (one strong source, or several that point the same way) and Low for three: unprotected contracts, changing fees and rents below the pitch, where we found no count.
The main limit is frequency. Only two risks come with an official count: the power hookups (64 of 80 stalled projects, June 2026) and the estates not taken over by the city (82% of 957, September 2026). The power count covers projects already delayed, not every building under way, and the city count includes old neighborhoods as well as new estates. Softec's stock covers Tijuana together with Rosarito and Ensenada.
Peso figures, such as Softec's average price per m² or the sample payment plan, stay in pesos, because they describe a market or an example rather than the price of one home. A projected yield is not the same as rent collected from a finished flat.
A sceptical reader could object that one stalled tower like KYO Ilán says nothing about another developer. We agree that a named case is not a rate. We use cases to show how things go wrong, official records to show which documents protect you, and Softec's new-home stock to test the claim that selling before the keys is easy. This is general information built from public data, not personal financial advice.
Key sources used for this analysis include June 2026 city statement: 64 of 80 delayed projects held up by lack of power, September 2026 interview: 32 substations, 5 more needed, September 2026 CFE works and the La Encantada substation, June 2026 report on developers paying for their own substations, June 2026 Canadevi on power shortages and water works paid by developers, August 2026 KYO Ilán buyers, refunds and developer timetable, April 2026 CMIC Tijuana on building-cost increases, September 2026 CMIC: some materials up as much as 30%, September 2026 Softec new-home stock by type, sales pace and price per m², April 2026 estates not handed over to CESPT, Real del Mar case, CESPT technical feasibility opinion and its 6-month validity, CESPT water contract for new developments and connection rights, September 2026 city data on estates not taken over and the special program, City requirements for approving new developments, September 2026 AMPI example of flats re-let at lower rents, January 2026 AMPI on rent cuts in late 2025, April 2026 march against the Cañada Azteca project, May 2026 signatures and permit dispute in Playas de Tijuana, Official text of NOM-247-SE-2021 on pre-sale contracts, PROFECO public register of standard contracts and Foreign Ministry rules for bank trusts in the restricted zone.
Spotted an error? Tell us, we fix it within days.