Summary
Yes, in Tulum and Mazatlán. Each has a named project years late, and a heavy stock of unsold new homes, which makes it harder for a developer to finish.
Eight more places carry some risk. Tijuana, Mérida, Cancún, Los Cabos and Puerto Vallarta have a heavy stock of unsold new homes or pre-sales that halved. Playa del Carmen has a stopped project, and Querétaro and Rosarito have land sold without permits or services.
Mexico City is lower risk on our measure: the problem there is fraud by fake sellers, not unfinished buildings.
Mexico's pre-sale contract rule (NOM-247) gives buyers rights, but it is not an escrow: your money goes to the developer.
Our Mexico pre‑construction table by place
Our table compares the risk of buying off-plan in 11 places in Mexico, from documented projects in trouble and the stock of unsold new homes.
For each place it gives our verdict, the projects in trouble and any official action, the price change over 12 months, the unsold new homes, the main risk for a pre-sale buyer, what to check before paying, a short explanation and our confidence in the figures.
If you want real answers from the field about a specific home or street, ask a pro in Mexico for free.
| Town |
Risky to buy off-plan? our short answer |
Projects in Trouble recent cases and official action |
Price Change last 12 months, resale |
Unsold New Homes how long to sell them (~ = our estimate) |
Main Risk for a pre-sale buyer here |
Check First before paying |
Why what drives the verdict here |
Data confidence iHigh: direct data for this town. Medium: one strong source, or several pointing the same way, with our own estimate. Low: few signals, an order of magnitude. |
|---|---|---|---|---|---|---|---|---|
| Tulum | High risk | Ocean Tulum: 3+ years late; 70+ unfinished buildings (lawyers' count) | −2% | Oversupply, sales halved | Projects without permits; title problems | Construction licence and environmental permit (MIA) | Sales halved since 2023 and many developers ran out of money; lawyers count 70+ unfinished buildings. | Medium |
| Mazatlán | High risk | Torre Triana, Torre Vita: years late; prosecutors took 3 of about 18 investigation files on a real‑estate group to court (Jul 2026) | Flat | 40 months of new stock | Delays as sales fell after 2024 | Developer's past towers delivered on time | Several towers are years late, and Sinaloa prosecutors took three investigation files on a real‑estate group to court in July 2026. | Medium |
| Playa del Carmen | Some risk | SUUT: 50+ buyers, work stopped in 2024 | +3% | 156 projects selling | Works stopped when money runs out | Who finances the works; pay by stages | 50+ SUUT buyers paid in full for units that weren't delivered; slow sales strain other projects. | Medium |
| Tijuana | Some risk | 64 of 80 delayed projects waiting for power hookups | −2% | 25 months of new stock (Softec) | Power and water connections | CFE power and water letters for the tower | About 2 years of new homes are still unsold, and most delays come from slow power hookups (CFE), but we found no named project years late. | Medium |
| Mérida | Some risk | 1,531 complaints (PROFECO Yucatán); undelivered lots north of the city | +8.5% | 40 months (flats) | Lots sold without permits | Subdivision permit; land not ejido | 40 months of new flats and many complaints about lots and homes not delivered, but no named project years late: buy built homes or check permits hard. | Medium |
| Cancún | Some risk | 8 developments closed for missing permits in 2 years (to Aug 2026), 2 more in Oct 2026; Zivalam complaints | +9.7% | 34 months of new stock | Lots and projects without permits | City licence; project not on the closure list | The city closed 8 developments without permits in two years and 2 more in October 2026; most were lots, not towers. | Medium |
| Puerto Vallarta | Some risk | — | Flat | Pre‑sale sales halved (480 → 227); ~1,500 units to 2028 | Delays in a slower market | Delivery date and penalty in the PROFECO contract | No named project in trouble, but pre‑sale sales halved in nine months (480 to 227) and 46% of listings aren't built yet: delays are the risk. | Medium |
| Los Cabos | Some risk | La Abundancia suspended (SEMARNAT); La Ribera: a judge opened criminal proceedings over a MXN 8M+ sale | +8.5% | Pre‑sale closings halved | Permits and environmental reviews | Environmental review (MIA) status | Pre‑sale closings halved this year, SEMARNAT suspended one project and a judge opened criminal proceedings over a pre‑sale in La Ribera. | Medium |
| Rosarito | Some risk | Cielo Residencial lot deliveries delayed | Flat | — | Lots sold before services | Roads, water and power before buying a lot | Lots sold before roads and services, with deliveries delayed. | Medium |
| Querétaro | Some risk | Prosecutors searched 7 sites over land sold without permits (Sep 2026) | +3% | 9,421 unsold new homes | Land sold without permits | Land title and land‑use permit | Prosecutors are chasing land sold without permits; check the land, not just the tower. | Medium |
| Mexico City | Low risk | Pre‑sale flat resold to another buyer (MXN 1.2M) | +4.6% | — | Fraud by fake sellers | Registry certificate; your own notary | Few problem projects; the risk is fake sellers, so use a notary from the start. | Medium |
Mexico's NOM-247-SE-2021 (in force since Sep 2022) requires pre-sale contracts to be registered with PROFECO and to disclose permits, delivery date and penalties. It is not an escrow: your money goes to the developer. Check the contract on PROFECO's public register (RPCA) and that the land and permits are in the developer's name. Rule (ours), place by place: High risk = a named project stopped or years late in the last 5 years, and measured heavy unsold stock (24 months or more, or new-home sales halved). Some risk = one of those two, or official action against projects in 2025-26 (closures, searches, suspensions). Low risk = none of these.
How we got these numbers. We analyzed 169 sources and 455 signals on Mexico, including state prosecutors (Yucatán, Querétaro, Quintana Roo), PROFECO, municipal closure notices, the press (El Economista, Bloomberg via El Financiero, Noroeste, ZETA, Novedades), Softec and The Red Search stock data and the NOM-247 text. The table itself uses 30 signals from 27 sources.
Source: TheLatinvestor property database, November 2026.
Ask a Mexico pro to check
the developer, for free.
They know which developers deliver on time.
Message a proIs it risky to buy pre-construction in Mexico now?
Yes, in Tulum and Mazatlán. Each has a named project years late, and enough unsold new homes (24 months or more at the current pace, or sales halved) to strain developers' cash.
Eight more places carry some risk: Tijuana, Mérida, Playa del Carmen, Cancún, Los Cabos, Puerto Vallarta, Rosarito and Querétaro each meet one of our tests. Mexico City is lower risk on our measure.
No city publishes a share of late projects, so our verdicts rest on documented cases, not on a full count.
Why is Tulum so risky?
Because sales collapsed while building went on. Homes sold in Tulum fell from 3,487 in 2023 to 1,711 in 2025, and many developers ran short of money. Lawyers count more than 70 unfinished buildings.
Ocean Tulum is one example. In June 2026, buyers who bought from 2022 said their flats were more than three years late, with parts still at the bare-structure stage and no firm delivery date.
Check the construction licence and the environmental permit (MIA) before you pay anything.
Has Mazatlán left buyers in unfinished towers?
Yes. Towers such as Torre Triana and Torre Vita are years late. In July 2026, Sinaloa's state prosecutor said her office had taken three investigation files on a real-estate group in Mazatlán to court, out of about 18 files opened after complaints in 2025 and 2026. She did not name the group.
The market makes it worse. Developers hold 6,442 unsold units, about 40 months of sales, and the local construction chamber says about 60% of projects started two years ago are going more slowly.
Is Tijuana high risk?
Some risk, on our measure. Developers hold about 25 months of unsold new homes, and Tijuana's economic development secretary said in June 2026 that 64 of 80 delayed housing projects were held up mainly by a lack of electrical infrastructure.
We found no named project years late, which our High risk needs. Before paying, ask for the power (CFE) and water letters for the tower.
Ask a Mexico lawyer
today, for free.
They check the registry before you pay anything.
Message a proIs Mérida risky?
For lots and land, yes. The trouble there is mostly plots north of the city sold without permits and never delivered, and land that is still communal (ejido).
Developers also hold about 40 months of new flats. We found no named tower years late, so Mérida gets Some risk, not High. Buy built homes, or check the subdivision permit and that the land is not ejido.
Could a fully paid condo in Playa del Carmen go undelivered?
It has happened. At SUUT, more than 50 buyers, some foreign, paid a total of about MXN 214 million for flats that were never delivered. Work stopped in 2024, linked to the developer's alleged debts with a lender.
That one case is why Playa del Carmen gets Some risk. Ask who finances the works, and pay in stages tied to progress.
Is Cancún safer than Tulum for a pre-sale?
Yes, but not risk-free. Cancún's city has closed developments for missing permits. In October 2026 it closed the Tolteca and Azteca private streets, whose lots were sold on social media without permits.
Most closures hit lots, not towers. Cancún also has about 34 months of unsold new condos, so check that the project is not on the city's closure list and has its licence.
Do Los Cabos's luxury projects avoid these problems?
No. SEMARNAT, the environment ministry, suspended La Abundancia pending an environmental review. In La Ribera, a judge opened criminal proceedings over a pre-sale worth more than MXN 8 million.
Most Los Cabos projects are big branded developments with deep pockets, but pre-sale condo closings halved in the first nine months of 2026 (217 to 108). That gives Some risk.
Ask a Mexico agent
for free, before you sign.
They can visit and tell you what they see.
Message a proWhat about Querétaro and Rosarito?
The risk there is land. Querétaro’s prosecutors carried out seven searches in September 2026 in fraud investigations over land sales, and secured the properties. In Rosarito, lots at Cielo Residencial were sold before roads and services, and deliveries were delayed.
Check the land title and land-use permit first, not just the tower.
Is Puerto Vallarta lower risk?
Not on our measure: it gets Some risk. Pre-sale sales fell by more than half, from 480 to 227 in the first nine months of 2026, and 46% of homes listed for sale are not built yet. We found no named project in trouble, but in a slow market, delays are the main risk.
Check the delivery date and the penalty for delay in the contract, and that the contract is registered with PROFECO.
Is Mexico City safer for pre-sale buyers?
We found few problem projects. The risk there is fraud: in one 2026 case, a pre-sale flat was sold to a second buyer, who lost MXN 1.2 million.
Use your own notary from the start, and get a registry certificate on the day you sign.
What protection does the law give?
Some. NOM-247-SE-2021, in force since September 2022, requires pre-sale contracts to be registered with PROFECO and to state the permits, the delivery date and the penalties.
It is not an escrow. Your money goes to the developer. A bank trust (fideicomiso) lets a foreigner hold a home near the coast, but it doesn't protect a deposit if the building is never finished.
So, is it risky to buy pre-construction in Mexico now?
Yes in Tulum and Mazatlán, where named projects are years late and unsold homes pile up. Some risk in Tijuana, Mérida, Playa del Carmen, Cancún, Los Cabos, Puerto Vallarta, Rosarito and Querétaro.
If you buy off-plan anywhere, check four things before paying: the land is in the developer's name, the permits exist, the contract is on PROFECO's register, and the developer has delivered other buildings on time. Then pay in stages, never everything up front.
Our methodology
Our data runs through November 2026. We compare the risk of buying off-plan in 11 places in Mexico.
We analyzed 169 sources and 455 signals on Mexico, including state prosecutors and city governments, PROFECO, SEMARNAT, the NOM-247 text, Softec and The Red Search stock data, MLS reports and the press. The table itself uses 30 signals from 27 sources.
Each place is rated on its own documented cases: a named project stopped or years late, official action against projects in 2025-26 (closures, searches, suspensions), and the stock of unsold new homes. Case counts come from the press and prosecutors, not a complete register. Legal wording follows the source.
High risk means a named project stopped or years late in the last five years and a heavy measured stock of unsold new homes (24 months or more, or new-home sales halved). Some risk means one of those two, or official action against projects in 2025-26. Low risk is none of these. Places where we found no documented pre-sale problem (Guadalajara, Monterrey, San Miguel, Lake Chapala, Oaxaca, Puerto Peñasco) are left out. This is general information built from public data, not personal financial advice.
Key sources used for this analysis include Palco Noticias: Ocean Tulum buyers report delays of more than three years, June 2026, Bloomberg via El Financiero: Tulum's unfinished projects, Expansión: Tulum sales and construction, October 2026, Ríodoce: Sinaloa prosecutor takes three fraud files to court, July 2026, Centro Urbano: Mazatlán unsold new homes (Softec), TV Pacífico: Mazatlán construction slowing, July 2026, NDT: 64 of 80 delayed Tijuana projects held up by power, June 2026, Centro Urbano: Tijuana unsold new homes (Softec), Por Esto: SUUT buyers in Playa del Carmen, April 2026, City of Cancún: closure of Tolteca and Azteca, October 2026, SEMARNAT: La Abundancia suspended and under review, BCS Noticias: La Ribera case, criminal proceedings opened, Querétaro prosecutors: seven searches over land sales, September 2026, N+: Mexico City pre-sale fraud, August 2026, Diario Oficial: NOM-247-SE-2021, PROFECO: public register of contracts and Mexico Life: Puerto Vallarta pre-sales, Q3 2026.
Spotted an error? Tell us, we fix it within days.