Summary
Somewhat. Most projects in Bogotá get built, and buyers' money usually goes through a trust company. But recent cases show what can go wrong.
Two of the seven risks in our table read High risk, because Bogotá buyers have waited years or could lose the home: Acanto, in Engativá, was promised for 2023 and is now promised for December 2026, and El Peñasco, a luxury project in Rosales, went into reorganization in 2024.
The other five read Some risk, each with a recent fine, ruling or published rise. In May 2026 the consumer regulator (SIC) fined Constructora Bolívar COP 1.31bn for moving delivery dates on a social-housing project.
More buyers are walking away. In Bogotá and Cundinamarca, 3,679 new-home purchases were cancelled in the first quarter of 2026, 11.5% more than a year earlier, and 33.4% more in pre-sale. More than half cited trouble getting a loan.
Buying off-plan saves little. New-home prices rose 8.6% in the year to mid-2026, about as fast as resale.
We would buy off-plan only from a builder with delivered projects, with payments into a trust, a fixed price, a delivery date with a penalty, and a loan pre-approved before signing.
Our Bogotá pre‑construction risk table by type of risk
Our table lists seven risks that off-plan buyers face in Bogotá, each with a recent case, how often it happens, what protects you and why we rate it as we do.
Rows are types of risk, because no share of late or failed projects is published by area. The rule behind each risk level is written under the table.
If you want real answers from the field about a specific home or street, ask a pro in Bogotá for free.
| Type of risk |
Risky to buy off-plan? our short answer |
What Happens in plain words |
Bogotá Case named in the press or by the SIC |
How Often the figure we found |
What Protects You before you sign |
Why what drives the verdict here |
Data confidence iHigh: direct data for this type of risk. Medium: one strong source, or several pointing the same way, with our own estimate. Low: few signals, an order of magnitude. |
|---|---|---|---|---|---|---|---|
| Late delivery | Some risk | Keys come one to three years after the promised date. | Buenavista Living (Constructora Bolívar, social housing): SIC fine of COP 1.31bn, May 2026 | About 30 complaints on that project. Nationally, 2,818 complaints and 3,255 lawsuits, and 38 builders sanctioned (SIC, Jan 2024-Oct 2025) | A delivery date and a penalty for delay in the contract | The SIC fined one of Colombia's biggest builders in May 2026: delivery dates moved at least three times. It can still appeal. | Medium |
| Abandoned works | High risk | The builder stops; buyers have paid the down payment and wait. | Acanto (Constructora Mevic, Engativá): promised for 2023, now promised for December 2026 | 324 complaints against its trust company nationwide, Jan 2025-May 2026 (Superfinanciera, via Noticias Caracol) | Check the builder's other projects and the fiduciary's "punto de equilibrio" release | Families paid their down payment through a trust and still wait: the trust holds money, it does not finish buildings. | Medium |
| Builder in insolvency | High risk | The company enters reorganization and deliveries freeze. | El Peñasco (Planinco, luxury flats in Rosales): entered reorganization in 2024 (latest public report, Aug 2024) | About COP 27bn of debts and about 34 lawsuits (Pulzo, Aug 2024) | Read the builder's filings at the Supersociedades; avoid tiny one‑project companies | A luxury project in the north still froze: price is no protection when the builder runs short of cash. | Medium |
| Penalty if you back out | Some risk | You lose part of what you paid if you cancel. | SIC ruled a 30% penalty clause abusive (Oct 2025) | 3,679 withdrawals in Bogotá and Cundinamarca in Q1 2026, +11.5%; pre‑sale +33.4% | Cap the penalty in the contract; the SIC can void abusive clauses | More buyers walked away in early 2026, mostly in pre‑sale. A fair contract caps what you lose. | Medium |
| Loan refused at delivery | Some risk | The bank won't lend the rest when the flat is ready. | Withdrawals up 11.5% in Q1 2026 in Bogotá and Cundinamarca, 53% for lack of financing (Camacol B&C) | Central bank rate up from 9.25% to 12.25% in a year; 30% paid before keys, 70% by mortgage | Get a pre‑approved loan; plan cash if you are a foreign buyer | With the central bank at 12.25%, loans are dearer than when you signed: have a plan B. | Low |
| Misleading ads | Some risk | Finishes, sizes or amenities differ from the brochure. | Bolívar fined for ads on Buenavista Living (2026) | Part of the 2,818 national complaints | Keep the brochure and the price list; demand specs in the contract | The same 2026 fine covered misleading publicity: keep every document you were shown. | Medium |
| Defects after delivery | Some risk | Services missing or poor quality once you move in. | Puerta del Rey (Agora Construcciones, Usme): SIC fine of COP 1.16bn, Nov 2023 | 302 court rulings against builders nationwide (SIC, Dec 2025) | A 10-year structural warranty applies; document defects fast | A 2023 SIC fine: homes handed over without gas, water or power, some never handed over. Buyers won, years after paying. | Medium |
New-home prices in Bogotá and Soacha rose 8.6% in the year to mid-2026 (DANE), about the same as resale (+8.9%), so pre-sale saves little versus a finished flat. Rule (ours), risk by risk: High risk = a Bogotá project since 2023 where buyers waited years or could lose the home. Some risk = a case since 2023 that ended in a fine or ruling by the SIC, or a published rise in buyers losing money. Low risk = neither. Complaints go to the SIC (Superintendencia de Industria y Comercio).
How we got these numbers. We analyzed 98 sources and 291 signals on Bogotá (DANE, Catastro, the city's housing observatory, Camacol, Aptología, Inside Airbnb, AirDNA, the SIC, the press); about 20 on pre-sale shaped this table: SIC rulings and statistics, Camacol Bogotá-Cundinamarca on withdrawals, Caracol and Noticias Caracol (Acanto), Infobae (El Peñasco, Buenavista), Bancolombia and Asofiduciarias on down payments and trusts. The table itself uses 15 signals from 9 sources.
Source: TheLatinvestor property database, November 2026.
Ask a Bogotá pro to check
the developer, for free.
They know which developers deliver on time.
Message a proIs it risky to buy pre-construction in Bogotá now?
Somewhat. Two of the seven risks in our table read High risk and five read Some risk.
High risk means a Bogotá project since 2023 where buyers have waited years or could lose the home. Some risk means a recent case that ended in a fine or ruling, or a published rise in buyers losing money.
Nationally, buyers of new homes filed 2,818 complaints and 3,255 lawsuits with the SIC from January 2024 to October 2025, and the SIC sanctioned 38 builders for more than COP 5,777M, it said in December 2025.
Most projects still get delivered, but a big name is no guarantee, as the Bolívar fine below shows. Buyers who cannot get a loan at delivery are the other weak point.
Can a big builder deliver years late?
Yes. In May 2026, the SIC fined Constructora Bolívar, one of Colombia's biggest builders, COP 1,306,426,800 over Buenavista Living, a social-housing project in Bogotá.
The SIC found that the builder had moved the delivery date at least three times, which also moved the deed signing and changed the final price. It also found the advertising unclear, including on the fact that the flats were social housing. The decision followed about 30 complaints, and Bolívar can appeal.
A delivery date and a penalty for delay in your contract are what let you claim.
Can a project stop after buyers have paid?
Yes. Acanto, a project by Constructora Mevic in Engativá, was promised for 2023. Buyers of its second and third stages paid their down payments, then saw no workers on site, Noticias Caracol reported in July 2026.
The developer blamed the pandemic, protests, weather and policy changes, and now expects to deliver in December 2026. The trust company that holds buyers' money had 324 complaints against it nationwide from January 2025 to May 2026, according to the financial regulator.
That is why we rate this risk High.
Does a trust company guarantee the building gets finished?
No. A trust (fiducia) holds buyers' payments until the project reaches its break-even point (punto de equilibrio): enough sales, a licence and financing. Then the money goes to the builder.
That protects you before the project starts. Once the money is released, the trust does not finish the building. If the builder stops, buyers complain to the trust, then to the Superfinanciera, and wait.
Ask which trust holds the money, what conditions release it, and whether they have been met.
Ask a Bogotá lawyer
today, for free.
They check the registry before you pay anything.
Message a proCan a luxury builder go bust?
Yes. El Peñasco, a project of luxury flats in Rosales by Planinco, entered reorganization in 2024 with about COP 27bn of debts and about 34 lawsuits, Pulzo reported.
A high price is no protection when the builder runs short of cash. Check the builder's filings with the Superintendencia de Sociedades, and be wary of a company set up for a single project.
Can you lose your down payment if you back out?
Part of it. Contracts often set a penalty if the buyer cancels. In October 2025, the SIC declared abusive a clause that made a buyer pay 30% of the contract value for breaching it, while the builder faced only bank interest for delivering late.
More buyers are backing out. In Bogotá and Cundinamarca, 3,679 purchases were cancelled in the first quarter of 2026, up 11.5%, and 33.4% more in pre-sale, Camacol found.
Read the penalty clause before you sign, and cap it.
What if the bank refuses the loan at delivery?
Then you can lose the flat. In Colombia, buyers usually pay about 30% during construction and borrow the rest when the flat is handed over.
Rates have risen since many buyers signed. The central bank rate is 12.25%, up from 9.25% at the end of 2025, and a new home loan outside social housing costs about 15.35% a year.
Of the buyers who walked away in early 2026, 53.3% cited trouble getting a loan or making the payments, Camacol found. Get a loan pre-approved before you sign, and keep cash in reserve.
Can the builder change the flat that was advertised?
It happens. The 2026 fine on Constructora Bolívar also covered advertising that was unclear and late.
Keep every brochure, floor plan and price list you are shown, and ask for sizes, finishes and parking in the contract itself.
Ask a Bogotá agent
for free, before you sign.
They can visit and tell you what they see.
Message a proWhat if the new flat has defects?
You can claim, but it takes time. In November 2023, the SIC fined Agora Construcciones COP 1.16bn over Puerta del Rey, a social-housing project in Usme: homes without gas, water or power connections, unfinished grounds, some homes never handed over and a third stage never built.
Nationally, the SIC's courts ruled for buyers 302 times from January 2024 to October 2025. Write down defects as soon as you move in.
Does buying off-plan save money?
Not much right now. DANE's new-home price index for Bogotá and Soacha rose 8.6% in the year to mid-2026, about the same as resale (8.9%).
You pay in instalments and get the flat later, but at today's prices. Unless a builder offers a clear discount on a finished flat, the waiting and the risks are not paid for.
So, is it risky to buy pre-construction in Bogotá now?
Somewhat. Two of the seven risks in our table read High risk and five read Some risk, each based on a recent Bogotá case or ruling.
Buy off-plan only from a builder with projects delivered on time, pay into a trust, and fix the price, the delivery date and a penalty for delay in writing. Get your loan approved first.
If any of that is missing, a finished flat costs about the same and carries none of these risks.
Our methodology
Our data runs through November 2026. We list seven risks that off-plan buyers face in Bogotá, each with a recent case from SIC decisions, the financial regulator or the press, and rate each with a written rule: High risk for a Bogotá project since 2023 where buyers waited years or could lose the home, Some risk for a case since 2023 that ended in a fine or ruling by the SIC, or a published rise in buyers losing money, Low risk for neither.
Complaint counts are national, not Bogotá-only. Withdrawals are Camacol figures for Bogotá and Cundinamarca together. We use the legal wording of the sources and do not name private persons.
We analyzed 98 sources and 291 signals on Bogotá, including the SIC, DANE, Camacol, Banco de la República and the press. The table itself uses 15 signals from 9 sources. This is general information built from public data, not personal financial advice.
Key sources used for this analysis include SIC, 8 May 2026: Constructora Bolívar fined COP 1,306,426,800 over Buenavista Living, Noticias Caracol, Séptimo Día, 5 July 2026: Acanto, Engativá, Pulzo, 19 August 2024: El Peñasco, Rosales, in reorganization, SIC, 30 December 2025: complaints, lawsuits, fines and rulings, January 2024 to October 2025, SIC, 30 October 2025: 30% penalty clause declared abusive, SIC, 1 November 2023: Agora Construcciones fined over Puerta del Rey, Usme, Portafolio, 21 April 2026: withdrawals up 11.5% in Bogotá and Cundinamarca, DANE, new-home price index, second quarter of 2026, DANE, resale price index, Bogotá, Banco de la República, 30 October 2026: rate held at 12.25%, Bogotá housing observatory, 23 October 2026: cancellations and financing at delivery, Asofiduciarias: how property trusts and their release conditions work and Superintendencia de Notariado y Registro: official title certificates.
Spotted an error? Tell us, we fix it within days.