Summary
Yes, Bocagrande still floods, but less and in fewer places: the Caribbean side is now largely protected, while the COP 168 billion drainage works for the low bay-side streets were only 31% done in mid-September 2026.
Recent events back that up. Heavy rain flooded Bocagrande streets in September 2025, and high tides put water on the road at the Naval Base entrance in November and December 2025, in two separate episodes.
There are two separate problems. Waves from the sea have been tamed along the finished beaches; rainwater that can't drain into a high bay has not, which is why the city launched the “4 en 1” project in 2026.
The sea defenses have passed a real test. In the February 2024 mar de leva, the protected beaches between roughly Calles 10 and 15 stayed intact while nearby streets flooded, and Cartagena now counts 2.15 km of coastal protection and six groynes.
Heavy rain is still the main risk. When a storm arrives at high tide, gravity drainage slows to a crawl, and the 2025 rain floods showed the old network can't cope.
Tides alone can do it too. In November 2025 the city's traffic authority warned water could reach about 60 centimeters in vulnerable spots during spring tides, with no storm needed, which is why the new network adds retention valves.
The worst spot is the entrance to Bocagrande around the Naval Base, flagged again in both late-2025 tide episodes; the stretch from the Portomarine building gets its own collectors, and Avenida Chile is the other big target.
Things are better than five years ago: Playa 3 reopened in 2025, Playa 2 was handed over on 6 September 2026, phase 1 of the coastal works is about 93% done and Playas 1 to 5 are due in April 2027.
The drainage is the unfinished part: 29.6% in July 2026, 31% on 14 September, and the city announced a first finished section on 14 October 2026, with four pumping stations still to come and completion aimed at 2027.
Until then, living in Bocagrande means detours and works: contraflows at Carrera 3 and Calle 10, a storm tank going in on Avenida Chile, and a bay-side wall that will widen the promenade by 5 meters.
The long-term pressure stays. Cartagena's relative sea level rose about 7 mm a year in 2000–2019, around 41% of it because the land is sinking, and wider beaches only handle the wave side of that.
A 20th-floor apartment won't take water, but that doesn't take you out of it. Garages, generators, electrical rooms and elevators sit at street level, and salt water corrodes them fast.
Flood risk doesn't show up as a neighborhood discount. Bocagrande apartments list at a median of about US$3,084 per m², close to Castillogrande's US$3,139, so the gap is between buildings, not districts.
Our take: flooding alone isn't a reason to skip Bocagrande, but check the building's garage, basement history and the drainage section on its street, and don't pay today for a fix due in 2027.
Ask an agent who knows
Cartagena, for free.
They know which streets are loud at night and which feel safe.
Message a proWhat has flooded in Bocagrande recently?
Streets, mostly, and it keeps happening when heavy rain or unusually high tides hit Cartagena.
Recent events make that hard to dispute. El Universal reported flooded streets in Bocagrande during intense rain in September 2025. In November, Cartagena's traffic authority again identified the area around the Naval Base as vulnerable during exceptionally high tides. Then, during another high-tide episode in December, photographs showed water covering the entrance to Bocagrande and slowing traffic.
The important change is frequency and location. Bocagrande is better protected along parts of its Caribbean-facing coastline than it used to be, so older images of widespread seawater overtopping should not be treated as a perfect description of conditions today. Yet recurrent flooding around low streets and the bay-side drainage system is still happening.
The strongest recent evidence comes from the city's own construction program. Cartagena is building a COP 168 billion (about $52.6 million) flood-control project for Bocagrande and Castillogrande. El Universal put it at 31% complete on 14 September 2026, and the city announced its first finished section only on 14 October 2026. You don't spend that kind of money on a problem that has gone away.
So Bocagrande has improved, but flooding is clearly not over.
| Type of flooding | Still happening? | Recent evidence | Situation today |
|---|---|---|---|
| Heavy-rain street flooding | Yes | Bocagrande affected during major rain in 2025 | Still possible |
| High-tide flooding | Yes | Naval Base area affected repeatedly | One of the clearest remaining risks |
| Wave overtopping | Reduced in protected sections | New coastal works performed well in previous rough-sea events | Much better than before |
| Slow drainage and ponding | Yes | Major drainage reconstruction underway | Still unresolved |
| Long-term sea-level pressure | Yes | Cartagena has unusually fast relative sea-level rise | Growing underlying risk |
Why does Bocagrande flood even though Cartagena has already built coastal defenses?
Bocagrande still floods because Cartagena has improved the oceanfront faster than it has fixed the neighborhood's drainage system.
That explains much of the apparent contradiction.
Along the Caribbean side, Cartagena has built groynes, rock defenses, wider beaches and new drainage infrastructure. Those works help absorb waves, reduce coastal erosion and protect Avenida Primera.
The bay side has a different problem. Rain falling inside Bocagrande needs somewhere to go, and high water around Cartagena Bay can make that difficult. When the receiving water is high enough, gravity drainage slows down. In some locations, tidal water can also push back through poorly protected outlets.
That is why the newer “4 en 1” project includes underground collectors, retention valves, stormwater storage and pumping stations. The design itself tells us what was still failing after the coastal works began.
There are really two separate questions here: can Caribbean waves still run directly into Bocagrande as easily as before, and can Bocagrande drain heavy rainfall efficiently when the surrounding water is high? The first problem has improved much faster than the second.
Have the new coastal defenses actually worked in Bocagrande?
Yes, Bocagrande's new coastal defenses have already shown that they can reduce flooding from waves and rough seas in the sections where they are finished.
One of the best real-world tests came during a strong mar de leva and high-tide event in February 2024. Streets in parts of Bocagrande and elsewhere in Cartagena flooded badly, with water high enough around some vehicles to cause serious disruption.
Yet the University of Cartagena team involved in designing the coastal project reported that the already-protected beaches between roughly Calles 10 and 15 remained intact. The project's director later said that Avenida Primera showed no accumulated water along the protected stretch between the Santo Domingo curve and Espolón 6.
That was a much stronger test than a computer rendering or a government promise. Rough seas actually arrived, nearby areas flooded, and the completed protection performed differently.
The physical scale of the works also matters. By 2025, Cartagena reported 2.15 kilometers of marginal coastal protection, about 998 meters of rock defense, six groynes measuring roughly 170 to 210 meters and more than one kilometer of a planned two-kilometer stormwater drainage system.
The program has kept going since. The rebuilt Playa 2 was handed over on 6 September 2026, phase 1 of the coastal protection was about 93% done, and Playas 1 to 5 are due in April 2027. The Caribbean-facing edge of Bocagrande has changed in a way you can measure.
| Coastal work | Reported scale | Main job | What it helps with |
|---|---|---|---|
| Marginal protection | 2.15 km | Protect coastline | Waves and erosion |
| Rock defense | ~998 m | Absorb wave energy | Rough seas |
| Groynes | 6 | Retain sand | Beach stability |
| Beach nourishment | Large widened sections | Create wave buffer | Wave run-up |
| Beachfront storm drainage | 1.05 km built out of 2 km at one reported stage | Remove rainwater | Avenida Primera flooding |
Why can heavy rain still flood Bocagrande?
Heavy rain can still flood Bocagrande because the neighborhood is very low, relatively flat and still depends on a drainage network that Cartagena is rebuilding.
The problem becomes worse when heavy rain arrives at the same time as a high tide.
Water naturally drains toward the bay or sea. If the outside water level is low, that process is easier. When the tide rises, the difference in elevation shrinks and water leaves more slowly. A drainage system that manages an ordinary shower can therefore struggle badly during a heavy storm at high tide.
Residents have seen that combination repeatedly. During intense rainfall in September 2025, Bocagrande was among the Cartagena neighborhoods reporting flooding and weather-related disruption. Only weeks later, high tides were creating another type of water problem.
The city's response goes far beyond cleaning a few drains. Cartagena is installing large stormwater collectors and pumps precisely because passive drainage has not been reliable enough.
Once that system is finished, heavy-rain flooding should become much less common. Today, though, the complete system is still being built.
Ask an agent in
Cartagena, for free.
Flooding, water cuts, noise: locals know before you do.
Message a proCan Bocagrande flood on a sunny day because of the tide?
Yes, unusually high tides can still put water into low parts of Bocagrande even without a major rainstorm.
This is one of the easiest parts of Bocagrande flooding to misunderstand. Water does not always arrive from the sky or directly over the beach.
Cartagena experiences periodic spring tides associated with lunar cycles. DIMAR has warned that these events can raise water enough to cause coastal overflow and road flooding in susceptible areas.
During a November 2025 spring-tide episode, Cartagena's traffic authority specifically flagged the Naval Base sector of Bocagrande. The authority warned that water levels in vulnerable parts of the city could reach around 60 centimeters. Another high-tide episode the following month brought water back onto streets around Bocagrande and created heavy congestion.
The new flood project includes retention valves partly for this reason. Their job is simple: allow stormwater to leave while stopping bay water from travelling back through the system.
High-tide flooding should become easier to control once the new network is complete, but Bocagrande still has that exposure today.
Where does Bocagrande flood the most now?
The entrance to Bocagrande around the Naval Base remains one of the clearest flood trouble spots today.
That location keeps appearing in recent reporting and in Cartagena's own engineering plans.
During high tides in late 2025, the Naval Base entrance was again singled out for road flooding. When Cartagena presented the “4 en 1” project, officials described the stretch between the Portomarine building and the Naval Base entrance as one of the most difficult points in the entire intervention.
The project therefore gives that area dedicated collectors rather than relying only on the wider neighborhood network.
Avenida Chile and other low bay-side streets are another major focus because they combine rainfall runoff with exposure to high bay levels. Historical reporting has also identified parts of Avenida San Martín and nearby streets where accumulated water interrupts traffic and access.
The risk changes over surprisingly short distances. A beachfront tower beside a completed coastal section can have a very different exposure from a building a few blocks away beside a low drainage point.
| Bocagrande area | Main flood problem | Recent picture | Risk today |
|---|---|---|---|
| Naval Base entrance | Tide plus drainage | Repeated trouble spot | High relative to neighborhood |
| Avenida Chile | Rain plus bay-side drainage | Core target of new project | Still significant |
| Interior low streets | Rain accumulation | Depends heavily on street elevation | Highly local |
| Protected Avenida Primera sections | Waves plus rain | Coastal protection already helping | Improved |
| Caribbean beaches with completed works | Rough seas and erosion | Much stronger physical buffer | Lower than before |
Is Bocagrande flooding less than it did a few years ago?
Yes, parts of Bocagrande are less exposed to flooding than they were a few years ago, particularly along the protected Caribbean shoreline.
We can say that with some confidence because the change is physical and has already been tested during severe weather.
Five years ago, much of the coastal-defense program existed only as an unfinished project. Since then, Cartagena has built long stretches of rock protection, six groynes, wider beaches and new stormwater structures. Playa 3 was reopened after major reconstruction in 2025, and Playa 2 followed on 6 September 2026.
During the 2024 rough-sea event, completed sections held up while nearby unprotected areas flooded. That is a pretty useful before-and-after comparison.
Still, neighborhood-wide flooding has continued. High tides affected Bocagrande repeatedly in late 2025, and the city started a second major flood project in 2026.
The improvement is real but uneven. The Caribbean-facing edge is simply further ahead than the underground drainage system.
How much of Bocagrande's new flood system is actually finished?
Bocagrande's main new drainage project is still far from finished, which is why claims that the neighborhood's flooding has already been solved are premature.
El Universal reported 29.6% overall progress in July 2026 and 31% on 14 September 2026, citing the city's infrastructure department. In early September the first stretch, at the Carrera 3 and Calle 10 intersection near the Naval Base, was repaved with new levels, rain gutters and storm-tank parts and reopened to traffic, and on 14 October 2026 the city announced the first finished section of the project.
That number is much more useful than repeated official promises of a “definitive solution.” It tells you where Bocagrande really stands: well past planning and excavation, with one stretch working, but most of the network, including the four pumping stations, still being built.
The pace has been uneven. Cartagena reported only 2.2% in May, then 29.6% in July as several fronts opened at once, but barely 31% by mid-September. Two fronts were working then: pipes, paving and gutters on one, demolition, excavation and pipe-laying past Carrera 13 on the other.
Construction has also revealed complications underground. During excavation, contractors found old asbestos-cement drinking-water pipes, and the city replaced the main with a 315 mm plastic (PEAD) pipe while the street was open.
Works started in mid-March 2026, and the contract allows roughly 20 months for the main works, so the city is aiming at 2027. Judging by the slower pace since July, we would not count on an early finish.
| Indicator | Earlier stage | Latest specific figure found | What it tells us |
|---|---|---|---|
| Overall “4 en 1” progress | 2.2% in May 2026 | 31% on 14 September 2026 (29.6% in July) | Fast start, slower since July |
| Preliminary stage | 96.5% in May | Essentially complete | Main works have taken over |
| First finished section | — | Announced 14 October 2026 | Only one stretch is working |
| Hydraulic network planned | — | More than 2.3 km | Large neighborhood-scale intervention |
| Pumping stations | — | 4 planned | Gravity drainage will no longer be the only option |
| Main construction horizon | — | Completion targeted in 2027 | Full flood protection is still ahead |
Ask a property manager in
Cartagena, for free.
They know which areas stay rented all year.
Message a proWill the new Bocagrande drainage project actually make a big difference?
Yes, the new Bocagrande drainage system could produce the biggest reduction in everyday flooding the neighborhood has seen in decades.
The design goes directly at the failure points responsible for many recent floods.
More than 2.3 kilometers of hydraulic infrastructure are planned. Stormwater will be collected through larger pipes and drains. Retention valves are designed to stop water from Cartagena Bay flowing backward. Storm tanks will temporarily hold runoff. Four automatic pumping stations are planned around Parque Navas, Coral Gables, La Concha and Punta Castillo.
The pumps are especially important. Bocagrande cannot always rely on gravity because the surrounding water sometimes rises too high. Mechanical pumping gives the neighborhood a way to move rainwater out even during those conditions.
The city also plans to raise parts of the road where technically feasible, which can remove some of the lowest points where water repeatedly accumulates.
We should still wait before calling the system successful. The real proof will come after several intense rainstorms and high-tide episodes once everything is operating together. For now, the engineering approach fits the problem unusually well.
What is it like to live in Bocagrande while the works go on?
Messier than usual, and it will stay that way into 2027. Since mid-March 2026, parts of Bocagrande and Castillogrande have had closures and detours. When the Naval Base intersection reopened in early September, the city kept a contraflow at Carrera 3 and Calle 10 so cars leaving Bocagrande can still reach Avenida San Martín and the old town.
The works are not only pipes. The same contract rebuilds Avenida Chile between the Portomarine building and the Club Naval, adds coastal protection on the bay side, renews parks and squares, and builds a wall that will widen the bay promenade by 5 meters. A storm tank that stores and pumps rainwater is going in on Avenida Chile.
If you buy to rent, ask the administración which streets around the building are still due to be dug up and when. Noise, dust and blocked garage access hurt reviews on short stays and can justify a lower price today, while the finished street should be worth more once the system works.
Is Bocagrande sinking too?
Yes, land subsidence is making Bocagrande's long-term flood problem harder because Cartagena's land is moving downward while the sea is rising.
A major Scientific Reports study combined tide gauges, GPS measurements and satellite radar observations across Cartagena. Researchers estimated long-term relative sea-level rise at about 5.98 millimeters per year between 1952 and 2019.
During 2000–2019, that rate reached roughly 7.02 millimeters per year.
Those numbers are unusually high. The researchers found that vertical land movement accounted for about 41% of Cartagena's observed relative sea-level change. GPS stations showed subsidence of roughly 2.85 to 5.71 millimeters per year, while satellite measurements found even larger localized movement in some parts of the wider city.
At around seven millimeters of relative rise a year, the change works out to roughly seven centimeters per decade if that rate persists.
Seven centimeters does not suddenly put an apartment tower underwater. For a flat drainage system working with small elevation differences, though, seven centimeters can materially change how frequently seawater reaches an outlet or how easily rainwater can escape.
| Measurement | Research finding | Approximate decade-scale equivalent | Why Bocagrande cares |
|---|---|---|---|
| Long-term relative sea-level rise | 5.98 mm/year | ~6 cm | Higher water against drainage system |
| 2000–2019 relative rise | 7.02 mm/year | ~7 cm | Faster recent historical trend |
| GPS subsidence | 2.85–5.71 mm/year | ~3–6 cm | Land itself is losing relative height |
| Share linked to subsidence | ~41% | — | Climate is only part of the problem |
| Additional subsidence-related rise estimated by 2050 | ~83 mm | ~8 cm | Infrastructure must keep adapting |
Does Bocagrande's wider beach really help with flooding?
Yes, the wider Bocagrande beaches help with coastal flooding because the extra sand gives waves more space to lose energy before reaching the road.
Beach nourishment can look cosmetic because the result resembles a larger tourist beach. Hydraulically, it creates a buffer.
A wave arriving at a narrow, eroded shoreline reaches urban infrastructure with relatively little room to break. A much wider beach gives that same wave a longer shallow zone across which to dissipate energy.
Groynes help keep that sand from moving away too quickly, while rock defenses protect the edge behind it.
Playa 3 provides a good example. When Cartagena reopened the reconstructed beach, the project had added a much larger strip of usable sand alongside new coastal infrastructure. Similar interventions across the Bocagrande shoreline have shifted the physical boundary between normal wave action and buildings inland.
A wider beach will not fix inland drainage, of course. The shoreline mainly reduces wave and erosion exposure. Bocagrande's pumps, drains and valves handle another part of the problem.
If you own an apartment on a high floor in Bocagrande, does flooding really matter?
Yes, Bocagrande flooding still matters to high-floor apartment owners because the vulnerable parts of a tower are usually downstairs.
A 20th-floor apartment is extremely unlikely to take floodwater directly. The garage entrance, basement, electrical rooms, pumps, elevators, backup generator and lobby may be another story.
Street flooding can prevent vehicles from entering or leaving. Water entering underground parking can damage cars and building equipment. Saltwater is particularly unpleasant because it accelerates corrosion. An elevator or electrical system placed low in the building can turn a shallow flood outside into a much larger operational problem.
That is why two apartments with nearly identical sea views can carry different flood risks.
When we assess a Bocagrande building, the useful questions concern the height of the garage ramp, past basement flooding, drainage pumps, backup power, critical electrical equipment and what happened during previous high-tide or heavy-rain events.
A high floor reduces personal exposure to water. It does not remove the building's exposure.
Ask an agent who knows
Cartagena, for free.
They know which homes sell fast and which sit for months.
Message a proIs flood risk already priced into Bocagrande apartments?
Not at neighborhood level. In October 2026 TuLugar listings put Bocagrande apartments at a median of about US$3,084 per m², almost the same as Castillogrande (US$3,139), which floods for the same reasons, and well above Manga (US$1,911). Buyers pay for the beach and the services first.
The old town is the real premium: about US$4,808 per m² in the Centro. Cartagena prices are also rising more slowly than the rest of the country: DANE's new-home price index was up 6.28% year on year in Q2 2026, against 8.80% nationally.
Where flood risk does show up is between buildings. A tower with a dry garage, high electrical rooms and a street already fixed is a different product from one whose basement took water in 2025, even at the same list price per m². Colombia Bound lists Bocagrande two-bedrooms at a median of about $344,000 with a 5.9% gross yield (October 2026), so a few months of disrupted rentals or a pump bill shared by the owners show up quickly in your return.
| Area (asking prices, October 2026) | Median per m² (US$) | Flood picture |
|---|---|---|
| Centro | 4,808 | Walled city, its own drainage issues |
| Castillogrande | 3,139 | Same “4 en 1” project as Bocagrande |
| Bocagrande | 3,084 | Bay-side streets still flood |
| Marbella | 2,186 | Open sea front |
| Manga | 1,911 | Low-lying bay island |
Should flood risk stop someone from buying property in Bocagrande?
No, flood risk alone should not stop someone from buying in Bocagrande today, but ignoring the exact building and street would be a mistake.
The neighborhood's flood story has changed enough that a blanket “Bocagrande floods” discount is becoming less useful.
Some oceanfront sections now have far better protection than they did several years ago. The new bay-side drainage project should improve another group of historically difficult streets. Yet buildings around low points, weak garage entrances or unfinished drainage sections still deserve much closer inspection.
We would therefore price the risk at property level.
Ask the administration whether the basement has flooded before. Find out what happened during the major rain and tide episodes of 2025. Check where the generator and electrical rooms are. Look at the garage ramp from street level. Determine whether nearby hydraulic works are already finished or merely included in the project.
That gives a much better answer than judging an entire peninsula from a few dramatic flood videos.
Could rising sea levels bring Bocagrande's flooding back even after the new works are finished?
Yes, rising relative sea levels mean Bocagrande will probably need more adaptation later even if the current projects work very well.
The Scientific Reports measurements are the clearest warning. Cartagena's historical relative sea-level trend has been running close to six to seven millimeters per year, partly because the city is subsiding.
If that kind of pressure continues for decades, today's pumps, road elevations, sea defenses and drainage outlets will eventually operate under tougher conditions than the engineers originally faced.
A separate modeling study focused on Bocagrande also found progressively larger flood exposure under higher sea-level scenarios later this century. Exact long-range percentages depend heavily on assumptions, so we would not use those projections to claim that a particular building will flood.
The near-term takeaway is simpler. Bocagrande is becoming an engineered coastline. Beaches will need replenishment, pumps will need maintenance, drainage capacity may eventually need expansion and defenses may need to be raised.
That does not make Bocagrande a bad place to live. It does mean flood protection will remain part of the neighborhood's infrastructure bill for a long time.
Does Bocagrande still flood? The final judgment
Yes, Bocagrande still floods, although the neighborhood is clearly better protected than it was a few years ago.
The recent evidence is strong enough for a firm answer. Bocagrande experienced rain-related flooding in 2025, the Naval Base area was repeatedly affected by high tides later that year, and Cartagena subsequently pushed ahead with a COP 168 billion flood-control project specifically designed for Bocagrande and Castillogrande.
That project is real, but it was only 31% done in mid-September 2026 and its first finished section was only announced on 14 October. Most of the system, including the pumps, is still ahead.
Meanwhile, the coastal defenses already built along the Caribbean side have performed well enough during rough-sea events to show that Bocagrande's exposure is changing. Parts of the shoreline now have wider beaches, groynes, rock protection and better drainage that simply did not exist several years ago.
So the old reputation is becoming too crude. Bocagrande still floods, particularly around low streets, the Naval Base entrance and sections affected by rain and high tides. Yet flooding is increasingly something we need to judge street by street and building by building rather than assume equally across the whole neighborhood.
Once the full drainage network, retention valves, storm tanks and four pumping stations have gone through several serious rain-and-high-tide events, we will have a much better test.
As of now, Bocagrande has made substantial progress against flooding. It has not solved it yet.
Our methodology
This article answers one question: does Bocagrande still flood, and where? We split it into recent floods, tide exposure, rain drainage, how the finished coastal defenses performed, progress on the new drainage system, the streets that flood most, and the long-term pressure from sinking land and rising sea level.
Recent observed events carry the most weight: El Universal's reports on the September 2025 rain and the November and December 2025 high tides, and its February 2024 report quoting the University of Cartagena on how the protected beaches held up in the mar de leva.
We treat finished works and works in progress differently. For the coastline we used the national disaster agency (UNGRD) and the city's own measurements of protection, rock defenses, groynes and drainage, plus the 2025 Playa 3 and September 2026 Playa 2 handovers. For the drainage we used the city's descriptions of the “4 en 1” project and El Universal's progress reports (2.2% in May, 29.6% in July, 31% on 14 September 2026), and the city's 14 October 2026 announcement of the first finished section. An announcement is never counted as protection.
Prices come from listing medians (TuLugar, Colombia Bound) and DANE's new-home price index for Q2 2026. Listing prices are asking prices, not sale prices.
Long-term pressure comes from peer-reviewed work: the Scientific Reports study of subsidence and relative sea-level rise in Cartagena (tide gauges, GPS and satellite radar) and a Frontiers in Marine Science study modelling future flooding in Bocagrande. We don't use those scenarios to say a given building will flood.
We checked these figures in October 2026. Dollar amounts use about COP 3,190 per US dollar (official TRM of 22 October 2026).
Limits: nobody publishes street-by-street flood depths or return periods for Bocagrande, and we could not find a whole-project progress figure after 14 September 2026. The real test of the new system will be several heavy storms at high tide once the pumps run.
Key sources used for this analysis include: El Universal on the September 2025 rains, El Universal on the November 2025 high tides, El Universal on the December 2025 high tides, University of Cartagena on the 2024 mar de leva, UNGRD coastal protection project, UNGRD on the performance of the protection, UNGRD on Playa 3, the city's coastal protection figures, the city on the April 2027 coastal deadline, the “4 en 1” launch, the hydraulic design and Naval Base works, the city on pipes, pumps and valves, the asbestos-cement pipes, the first finished section (14 October 2026), El Universal, May 2026 progress, El Universal, July 2026 progress, El Universal on the reopened Naval Base intersection, El Universal, 31% progress, TuLugar Cartagena market data, Colombia Bound Bocagrande, DANE IPVN Q2 2026, Scientific Reports on Cartagena subsidence, Frontiers in Marine Science on Bocagrande flooding.